Time to Negotiate Task
Switching Time?
by Darrel A. Raynor, PMP, CCP
(C) Copyright 1999 Data Analysis & Results, Inc.
Question"How do you allocate the extra time it costs when you have to
move people around between tasks?"
This is a frequent question from my clients and in my project
management classes. Project Managers frequently have to ask people to
drop what they are doing and work on other tasks. How should we record
the 'extra' time in the schedule that this causes? For example, if
Mary is working on an internal interface and I have to interrupt her
to have her work on record layouts for a newly discovered vendor file,
it will take her longer to do each task than if she could work on one
uninterrupted.
The idea here is not to discourage all reallocation of tasks, more to
record and think about the real results of having people switch tasks
on a regular basis. Project Managers are in the business of crises
reduction, not crises manufacture. Having a formal process for
re-estimating when people are moved from task to task can be another
tool for a Project Manager to strive for reality in all we do.
The goals of making this normally informal process formal are improved
estimates and better impact analysis through recognizing the reality
that it takes people time to switch from task to task. Further
refinement of your processes to include irritants to the Team can save
you turnover, morale issues, and can also help people grow in their
job by recognizing the real costs of our actions.
Suggestions
1. Write Down how you think Estimates Should Change. Check your
figures by keeping accurate actuals of both the interrupted task and
the new task. This is a judgment call, as most times you are not sure
how long the task would have taken without interruptions, much less
with one or more task reassignments. My general rule of thumb is to
increase the allocated time by 20% for short duration tasks for each
interruption. 10% can be used for medium length tasks and 5% for long
duration tasks.
2. You may want to make a list of the factors involved, such as
concentration breaking, programmer or other technician 'mindset',
organization and familiarization time, and anything else you can think
of that may cause more work or more time than if someone works on a
task from start to finish.
3. Create an assumptions statement to add to your project plan and
draft schedule line items to add to your schedule. Talk these over
with your Team to get their gut feel and experiences. Make sure you
have their buy-in for your attempt at changing these processes. This
will help cut down on grousing and further wasting time as people move
from task to task. It may also help with the perceived 'fairness' of
asking people to switch tasks, then holding them to their original
estimates.
4. Talk to your managers, sponsors, and other stakeholders during a
regular status meeting. Make sure you do your pre-work, and contact
the people with the authority or those who make recommendations that
carry weight. Prepare an agenda and distribute it ahead of time to
keep from surprising people.
Take the time to explain why you are striving to add this further
level of precision to the planning and scheduling process for your
projects. This form of impact analysis can further help refine your
estimates and in some cases can reduce the number of times you are
asked (forced?) to yank your people from task to task.
Resources
I have not been able to find any academic or other research on time
lost due to task changes. If readers have knowledge of any materials,
please let me know.
-------------------
Darrel A. Raynor is a Project Manager and Project Turn-around
Consultant. He consults, speaks, and writes on using technology in
business. He is a Project Management Professional (PMP), a Certified
Computer Professional (CCP), and has an MBA. Darrel's passion is
building and leading software application development project teams,
specializing in project planning, Year 2000, requirements, and project
execution. Mr. Raynor's core beliefs
include full disclosure, adherence to professional society codes of
ethics, open communication and teaching. Mentoring project leads and
managers is Mr. Raynor's delightful specialty. He founded Data
Analysis & Results, Inc. in 1985. Contact him at 972-935-9525 or DARaynor@DataAnalysis.com.
Trade names, Trade, and Service marks are the property of their
respective owners.
NOTE: Follow this link to submit
an article to Management In-Sight! newsletter@trainersdirect.com.
 |
|
The Trainers Directory will
not sell or otherwise distribute the information you share with us.
By requesting information from us, we infer you grant us permission to
stay in touch with you to advise you of similar services offered by the
Trainers Directory. If at any time you decide not to receive
correspondence from us, simply send us an e-mail,
and we will remove you from future distributions.
For more detail,
please read our "Privacy Policy". |